BW News - BrownWinick Law Firm

Cost-Plus Contracts - A New Warning For Contractors

Written by Michael Dee | Oct 21, 2019 6:00:44 PM

A recent decision from the Iowa Court of Appeals serves as a cautionary tale for contractors: Contractors must prove their actual costs under cost-plus contracts or they may not be paid.  

In Olmstead Construction, Inc. v. Otter Creek Investments, LLC, the contractor and owner entered into a cost-plus contract to build a convenience store. After receiving revised invoices, the owner was concerned about newly increased costs and withheld payment until the contractor explained, and provided documentation for, the additional costs. After 30 days, the owner hadn’t received an explanation of the costs and therefore hadn’t yet paid the invoices, so the contractor filed a mechanic’s lien. Two months later, the contractor petitioned to foreclose on its mechanic’s lien and added claims for breach of contract, seeking damages, prejudgment interest and attorney fees.

The owner disputed the contractor’s charges for equipment costs — a skid loader, fork lift, delivery truck, and other small tools — all of which the contractor owned. But because the contractor owned this equipment, it couldn’t produce receipts verifying its costs. During the lawsuit, the contractor offered two methods for calculating these costs: (1) the contractor’s estimate of the equipment cost based on over 20 years of experience, and (2) the equipment rate schedules provided by the Iowa Department of Transportation (IDOT). The Court, however, explained that both methods were speculative and held that, although charging for the use of contractor-owned equipment was fine, contractors must either prove the actual costs of using the equipment or include and agree to the cost in the initial contract with the owner. In other words, if the original contract had included a rate schedule for using the contractor’s equipment, the owner would have had to pay those costs because by signing the contract, the owner would have agreed to the schedule.

Another area of dispute was the contractor’s general refusal to provide the back-up for other expenses billed on the project. The Court of Appeals held that “a cost-plus contract, by nature, demands that the contractor maintain accurate and detailed expense records,” and that “any contract requiring an owner to reimburse a contractor’s costs implicitly allows the owner to approve the contractor’s accounting system and audit contract costs and pricing data . . . [a]nd if the owner disputes the billing, the burden is on the contractor to prove each and every item of expense.” The Court concluded that the owner’s refusal to pay the final invoices until the contractor provided the requested documents was not a default under the contract.

The take-away: contractors, include the costs of your own equipment in the original contract and be prepared to document every penny of expense you are charging under cost-plus contracts; owners, you have the right to request back-up documentation for any costs charged under a cost-plus contract.

If you have any questions or concerns regarding your current or future contracts, please reach out to one of our many experienced attorneys. We’re more than happy to help.